Lot completion and delivery appears after a run completes or a verified saved result is opened.

Lot times

Completion and delivery are seconds from simulation start. Cycle time is elapsed seconds from lot release.

Column

Meaning

Lot

The lot ID.

Wafers

The requested wafer count for the lot.

Cycle (s)

Elapsed time from lot release to fab completion.

Completion (s)

Lot release time plus simulated cycle time.

Delivery (s)

Completion time plus the sum of imported backend step durations. For a fab-only model, delivery equals completion.

Lot states

Time cells for unfinished lots show Not completed.

Status

Meaning

Completed

The lot completed its route.

Not released

The lot release time is after the simulation horizon.

Incomplete at horizon

The lot was released and is unfinished at the simulation horizon.

Totals

Result

Meaning

Completed wafers

Total wafers in completed lots.

Expected good dies · Poisson, Expected good dies · Murphy, Expected good dies · Negative binomial

Completed wafers × dies per wafer × the corresponding yield-model probability.

Overall delivery

The latest lot delivery time when every requested lot is complete; otherwise Not completed.

Related guides

Use vFactory: explore a fab and follow a design to wafer

Reference-fab layouts, process data and results use example assumptions.